Major plans for a 120-acre solar farm alongside the A50 on the outskirts of Derby

Plans for a 120-acre solar farm alongside the A50 on the outskirts of Derby have been submitted.

The scheme, submitted to South Derbyshire District Council by Noventum Power (Arleston Solar Limited), would see the solar farm and an electricity battery farm built on fields between the A50, the Trent and Mersey Canal and Stenson.

A decision will be made by the district council in the next few months.

If approved, the development would be able to provide power to 18,000 homes annually and reduce carbon emissions by 20,000 tonnes per year.

The proposed site is 100 metres away from another potential electricity battery farm on the opposite side of the canal, which was rejected by councillors in April and is currently being considered at appeal.

These new plans would involve a 43 megawatt solar farm – just below the current 50 megawatt limit at which a decision would be made by central government – and a 99.9 megawatt battery electricity storage system (BESS), which are all to be decided by local councils.

Plans are in motion to change the thresholds for national decisions on solar farms to 100 megawatts from December 31 this year.

If approved, the solar farm would be connected by cabling to the former Willington Power Station site, around 1.7 miles to the south-west.

The battery storage portion of the proposed development would include 26 shipping containers measuring 2.5 metres in height.

Construction would take 12-18 months “with an intensive period in the middle and less intensive activity at the beginning and end of that period”.

Construction traffic will use Arleston Lane, Wragley Way and other A-roads.

A report submitted with the application says: “The government has expressed the need for critical national priority infrastructure to be progressed as quickly as possible.

“It has established a strong need for increased solar and BESS deployment to ensure energy security and climate change targets are met. Both are urgent and of critical importance to the country.

“The scale of contribution and benefits in terms of meeting that need for a secure, cost-efficient, reliable solution in addition to the role the proposed development will play in decarbonising the energy sector and meeting net zero compared with combustion of fossil fuels is substantial.”

The report says site selection has been carefully considered and that the biggest challenge is finding grid connections – available in South Derbyshire at both the former Drakelow and WIllington Power Stations – leading to a particular hotspot in applications for solar power infrastructure.